Goodman metal works has undertaken a design ,build and installation project for PB Kent Fertilisers at Immingham.
The project was to replace their ageing fertiliser dryer 2550mm outside diameter and 21 metres long weighing 66 tons and associated drive and roller supports.
The installation included new support rollers and frames , chain drive arrangement including stainless discharge box.
The project was awarded early February and the be installed in July within the companies 2 weeks shut down period.
Support bogies and track was installed to make removal and installation of the driers easier due to the time restraints and the congestion of the production plant.